Oct 05, 2021
Work on streets to be repaved this year is scheduled to begin October 18. Initial work will include water main replacement in the second block of Olive Avenue and curb/sidewalk work on other streets; asphalt paving will likely be done in mid-November.
The City of Rehoboth Beach has contracted with George & Lynch to perform repair and repaving work on the following streets:
- Lake Drive: from Scarborough Avenue to Bayard Avenue
- Martin's Lane: from Christian Street to the library
- Olive Avenue: from the boardwalk to 2nd Street
- Stockley Street Extension: from State Road to the end
- Surf Avenue: from Columbia Avenue to Lake Avenue
In addition, the water main will be replaced on Olive Avenue between 1st and 2nd streets.
While work is taking place on specific streets, through access may be limited, but resident access to homes will be maintained at all times.
Work hours will be 8 am-5 pm Monday-Friday. Work is expected to be completed by the end of November. Please note that adverse weather conditions may cause delays.
More specific scheduling for individual streets will be shared with impacted residents and posted here as it is provided by the contractor to the city. Questions? Contact the Rehoboth Beach Communications Department or call 302-227-6181, ext. 522